The time taken to do a piece of work is inversely proportional to the number of men employed. If it takes 30 men to do a piece of work in 6 days, how many m...
The time taken to do a piece of work is inversely proportional to the number of men employed. If it takes 30 men to do a piece of work in 6 days, how many men are required to do the work in 4 days?
Answer Details
t = time taken and N = number of men t ∝ 1/N t = K/N K = Nt K = 30 * 6 K = 180 ∴t = 180/N 4 = 180/N 4N = 180 N = 180/4 45 men