Back to Development And Testing
N
Oak National Academy
Lessons written by expert teachers in England, each with slides, a video and quizzes.
Their topic:
Using IT in project management · Python programming project
For your topic:
Development And Testing · Information and Communication Technology (9-1) - 0983
Use these lessons alongside our lesson note, which covers your syllabus in full.
What this covers in your syllabus
The need to test the system before implementation Test designs, test strategies, test plan (test data, expected outcomes, actual outcomes, remedial action) following testing Test designs including the testing of data structures, file structures, input formats, output formats and validation routines Test strategies including to test each module, each function and the whole system The definition, characteristics and use of test data using normal, abnormal and extreme data The use of live data.
Not covered here. Our lesson note covers it.
2 lessons from Oak National Academy
1
Evaluate your project
2
Testing and refining a programming project
Lesson 1 of 2 · GCSE level, ages 14 to 16
Evaluate your project
By the end:
I can develop testing documentation to demonstrate how the product has been tested and use this test data to evaluate a completed project.
Key learning points
Creating a test plan helps you to outline what needs to be tested.
A testing table records what needs to be tested, who will do it, when it will happen and how success will be measured.
Performing tests helps to see which parts of the system work and which parts may need to be improved or modified.
Reviewing the original objectives helps you to determine whether the project met its goals.
Keywords
evaluation
reflecting on what has been done well and what could be improved
test plan
a document that sets out the tests that will be carried out during testing
A common mistake
Mistake: Testing should only be done at the end of a project.
In fact: It is good practice to test products during and at the end of a project.
A computing lesson by Oak National Academy licensed under the Open Government Licence (OGL) v3.0.
Read the licence
Lesson 2 of 2 · GCSE level, ages 14 to 16
Testing and refining a programming project
By the end:
I can test a programming project using a range of methods.
Key learning points
Testing is the process of checking that a program works correctly and meets all its requirements.
To test a program thoroughly, a range of data should be used, including normal, boundary and invalid data.
A good test plan includes clear tests with predicted outcomes.
If the actual results don't match the expected results, the program is checked for errors in a process called debugging.
Keywords
testing
the systematic process of checking that a program works as expected
debugging
the process of finding and correcting errors in program code
A common mistake
Mistake: A test plan should only include data that will cause a program to not work.
In fact: A test plan should contain a range of test data, including normal, erroneous and boundary.
Check what you learned
From Oak National Academy's exit quiz. Choose every answer that is right.
Why is it important to use different types of data when testing?
to make the test plan longer
to slow down the program
to check how the program handles all possible situations
to impress your teacher
Which statement about test plans is correct?
a test plan should contain normal, boundary and erroneous data
a test plan should only include data that makes the program fail
a test plan is only needed for large projects
a test plan is not useful for programmers
What should you do if your program’s actual results don’t match the expected results?
debug the program
ignore the problem
add more features
delete the test
Check answers
A computing lesson by Oak National Academy licensed under the Open Government Licence (OGL) v3.0.
Read the licence
The wording comes from each publisher. The layout and the links to your syllabus are ours.