Use the information below to answer questions Direct labour...................₦50 000 Beginning work-in-progress......₦4 000 Raw materials used................

Assessment: JAMB UTME - Principles of Accounts - 2005 Subject: Financial Accounting

Question 1 Report

Use the information below to answer questions Direct labour...................₦50 000

Beginning work-in-progress......₦4 000

Raw materials used..............₦18 000

Indirect labour.................₦4 000

Ending finished goods...........₦16 000

Ending work-in-progress.........₦9 000

Factory supplies used...........₦7 000

Selling expenses................₦25 000

Beginning finished goods........₦21 000

Other factory overheads.........₦19 000What is the cost of goods manufactured?

Answer Details
The cost of goods manufactured is the total cost incurred in the production of finished goods during a particular period. It can be calculated by adding the total manufacturing costs for the period to the beginning work-in-progress and then subtracting the ending work-in-progress. Total manufacturing costs = Direct labour + Raw materials used + Factory supplies used + Other factory overheads + Indirect labour Total manufacturing costs = ₦50,000 + ₦18,000 + ₦7,000 + ₦19,000 + ₦4,000 = ₦98,000 Therefore, cost of goods manufactured = Beginning work-in-progress + Total manufacturing costs - Ending work-in-progress = ₦4,000 + ₦98,000 - ₦9,000 = ₦93,000 Hence, the cost of goods manufactured is ₦93,000.

Download The App On Google Playstore

Everything you need to excel in your exams

Green Bridge CBT Mobile App
Personalized AI Learning Chat Assistant
200,000+ Exam Questions Across IGCSE, JAMB, WAEC & NECO
Over 3,900 Lesson Notes
Offline Support - Learn Anytime, Anywhere
Green Bridge Timetable
Literature Summaries & Potential Questions
Track Your Performance & Progress
In-depth Explanations for Comprehensive Learning