Cost schedule of a firm Output Total Fixed cost TFC(N) Total Variable Cost TVC (N) Total Cost TC (N) Average Variable AVC(N) Average Total ATC (N) Marginal ...

Assessment: WAEC SSCE - Economics - 1993 (Essay) Subject: Economics

Question 1 Report

Cost schedule of a firm

Output Total Fixed cost TFC(N) Total Variable Cost TVC (N) Total Cost TC (N) Average Variable AVC(N) Average Total ATC (N) Marginal Cost MC(N)
0 100 0 100 0 100 -
1 100 40 140 - - -
2 100 64 164 - - -
3 100 80 180 - - -
4 100 88 188 - - -
5 100 96 196 - - -

From the cost schedule in this table calculate the Average Variable Cost (AVC), Average Total Cost (ATC) and Marginal Cost (MC) of the firm. Show your working clearly.

Answer Details

We use three formulae. Average Variable Cost \( AVC = \dfrac{TVC}{Q} \), Average Total Cost \( ATC = \dfrac{TC}{Q} \), and Marginal Cost \( MC = \dfrac{\Delta TC}{\Delta Q} \) (the change in total cost when output rises by one unit).

Working

AVC = TVC \( \div \) Output:

  • Q = 1: \( 40 \div 1 = 40 \)
  • Q = 2: \( 64 \div 2 = 32 \)
  • Q = 3: \( 80 \div 3 = 26.67 \)
  • Q = 4: \( 88 \div 4 = 22 \)
  • Q = 5: \( 96 \div 5 = 19.2 \)

ATC = TC \( \div \) Output:

  • Q = 1: \( 140 \div 1 = 140 \)
  • Q = 2: \( 164 \div 2 = 82 \)
  • Q = 3: \( 180 \div 3 = 60 \)
  • Q = 4: \( 188 \div 4 = 47 \)
  • Q = 5: \( 196 \div 5 = 39.2 \)

MC = change in TC as output rises by 1 unit:

  • Q = 1: \( 140 - 100 = 40 \)
  • Q = 2: \( 164 - 140 = 24 \)
  • Q = 3: \( 180 - 164 = 16 \)
  • Q = 4: \( 188 - 180 = 8 \)
  • Q = 5: \( 196 - 188 = 8 \)

Completed schedule

OutputTFC (N)TVC (N)TC (N)AVC (N)ATC (N)MC (N)
01000100---
11004014040.00140.0040
21006416432.0082.0024
31008018026.6760.0016
41008818822.0047.008
51009619619.2039.208

Notice that AVC and ATC both fall as output rises, showing the firm is spreading its fixed cost of N100 over more units and enjoying increasing returns over this range.

Download The App On Google Playstore

Everything you need to excel in your exams

Green Bridge CBT Mobile App
Personalized AI Learning Chat Assistant
200,000+ Exam Questions Across IGCSE, JAMB, WAEC & NECO
Over 3,900 Lesson Notes
Offline Support - Learn Anytime, Anywhere
Green Bridge Timetable
Literature Summaries & Potential Questions
Track Your Performance & Progress
In-depth Explanations for Comprehensive Learning