Explain one procurement decision that could help a start-up manufacturer of electric scooters meet its objective of reliable production. It needs batteries,...

Assessment: Business 9225 | Paper 2 Mock 01 | Written Paper 2 Subject: Business - 9225

Question 1 Report

Explain one procurement decision that could help a start-up manufacturer of electric scooters meet its objective of reliable production. It needs batteries, tyres and electronic controllers from several businesses. A delayed controller delivery last month stopped the whole manufacturing line for two days, while customers waited for orders and sales were postponed.

(a) Identify one reason why a delay in one component can stop scooter manufacturing. [1]
(b) Explain one benefit of using an approved-supplier list. [2]
(c) Which component should procurement treat as a priority if it is required for every scooter and currently has the longest delivery time? [1]
(d) What is meant by lead time in this context? [1]
(e) Explain one reason why the business may hold a small buffer stock of controllers. [1]

Answer Details

(a) All required components are needed to complete a scooter, so a missing component prevents final assembly [1].

(b) An approved-supplier list identifies suppliers already checked for quality and reliability [1]. Procurement can order more quickly and reduce the risk of unsuitable materials or supply disruption [1].

(c) The electronic controller should be treated as the priority [1], because it is required for every scooter and has the longest delivery time.

(d) Lead time is the time between placing an order and receiving it [1].

(e) The business may hold a small buffer stock of controllers so manufacturing can continue if a delivery is late or demand rises unexpectedly [1]. Buffer stock is extra stock held to protect production against uncertainty.

Download The App On Google Playstore

Everything you need to excel in your exams

Green Bridge CBT Mobile App
Personalized AI Learning Chat Assistant
200,000+ Exam Questions Across IGCSE, JAMB, WAEC & NECO
Over 3,900 Lesson Notes
Offline Support - Learn Anytime, Anywhere
Green Bridge Timetable
Literature Summaries & Potential Questions
Track Your Performance & Progress
In-depth Explanations for Comprehensive Learning