N Direct material 2,500 Direct labour 5,000 Direct expenses 1,000 Overhead expenses 1,500 Use the information contained in the table to answer the question ...

Ìdánwò: JAMB UTME - Principles of Accounts - 2018 Ẹ̀kọ́: Financial Accounting

Ibeere 1 Ìròyìn

  N
Direct material 2,500
Direct labour 5,000
Direct expenses 1,000
Overhead expenses 1,500

Use the information contained in the table to answer the question below.

From the data above, compute the prime cost. 

Awọn alaye Idahun
To compute the prime cost, we need to add the cost of direct materials, direct labour, and direct expenses. Adding the figures for direct materials, direct labour, and direct expenses gives us: 2,500 + 5,000 + 1,000 = 8,500. Therefore, the prime cost of the product is N8,500. The prime cost represents the total cost of direct materials, direct labour, and direct expenses that are directly attributable to the production of a product or service. This cost is essential to know for any manufacturing or production-oriented business, as it is the basis for determining the total cost of production.

Ṣe igbasilẹ ohun elo naa lori Google Playstore

Gbogbo ohun ti o nilo lati ṣe dara julọ ninu JAMB, WAEC ati NECO.

Green Bridge CBT Mobile App
Asiko ẹkọ AI ti ara ẹni Chat Assistant
Ìbéèrè ìdánwò IGCSE, JAMB, WAEC ati NECO tó ju 200,000 lọ
Fiwọn 1200 Awọn akọsilẹ Ẹkọ ju.
Atilẹyin Aisinipo - Kọ ẹkọ Nigbakugba, Nibi gbogbo
Tẹ̀dí Green Bridge
Àkójọpọ̀ Ìtàn Lítíréṣọ̀ & Ìbéèrè Tó Lè Dáyéé ṣẹ́lẹ̀
Tẹle iṣẹ ṣiṣe rẹ ati ilọsiwaju rẹ.
Àlàyé tí ó jinlẹ̀ fún ìmòye tó jinlẹ̀.