Information and Communication Technology (9-1) - 0983 CIE

Implementation

Visão Geral

The new system is built and tested, so now it has to take over from the old one in the real workplace. That handover is implementation, and how it is done matters enormously. Switch everything across overnight and you save money but risk disaster if the new system fails; run both systems together and you are safe but pay twice. Choosing the right changeover method for the situation is one of the most important decisions in the whole life cycle.

In this lesson you will learn the four methods of changeover: direct, parallel, pilot and phased. You will learn exactly how each one works and weigh up the advantages and disadvantages of each, so that, given a real scenario such as a hospital or a chain of shops, you can recommend and justify the most suitable method.

Objetivos

  1. System implementation.
  2. Characteristics, uses, advantages and disadvantages of the four methods of implementation, direct changeover, parallel running, pilot running, phased implementation.

Nota de Aula

Implementation is the moment the new system meets reality. Up to now everything has happened in development, but here real staff, real data and real customers depend on the system working. The chosen changeover method is a balance between cost, risk and disruption. A bank moving customer accounts, a hospital handling patient records and a small shop updating its tills face very different risks, so the method that suits one would be reckless or wasteful for another. Knowing the four methods and their trade-offs lets you match the method to the situation.

Disponível na aplicação Green Bridge

Transfira a aplicação Green Bridge CBT para o seu telemóvel ou computador para aceder a notas de aula completas, questões de prática e muito mais.

Notas de aula completas com diagramas
Assistente de aprendizagem com IA
Estude offline, a qualquer hora e em qualquer lugar
Disponível para Android, Windows, macOS e Linux

Avaliação da Lição

Parabéns por concluir a lição em Implementation. Agora que você explorou o conceitos e ideias-chave, é hora de colocar seu conhecimento à prova. Esta seção oferece uma variedade de práticas perguntas destinadas a reforçar sua compreensão e ajudá-lo a avaliar sua compreensão do material.

Irá encontrar uma mistura de tipos de perguntas, incluindo perguntas de escolha múltipla, perguntas de resposta curta e perguntas de redação. Cada pergunta é cuidadosamente elaborada para avaliar diferentes aspetos do seu conhecimento e competências de pensamento crítico.

Use esta secção de avaliação como uma oportunidade para reforçar a tua compreensão do tema e identificar quaisquer áreas onde possas precisar de estudo adicional. Não te deixes desencorajar pelos desafios que encontrares; em vez disso, vê-os como oportunidades de crescimento e melhoria.

  1. Which changeover method runs the old and new systems together for a time? A. Direct changeover B. Parallel running C. Pilot running D. Phased implementation Answer: B
  2. A method that introduces the new system into one branch first is called: A. Direct changeover B. Phased implementation C. Pilot running D. Parallel running Answer: C
  3. Which method carries the greatest risk if the new system fails? A. Parallel running B. Pilot running C. Phased implementation D. Direct changeover Answer: D
  4. Introducing the new system one part at a time, proving each before adding the next, is: A. Pilot running B. Phased implementation C. Direct changeover D. Parallel running Answer: B
  5. Which is a disadvantage of parallel running? A. There is no backup if the new system fails B. It is expensive because data is entered into two systems C. Benefits are felt immediately D. Only one branch is affected by failure Answer: B

Disponível na aplicação Green Bridge

Transfira a aplicação Green Bridge CBT para o seu telemóvel ou computador para aceder a notas de aula completas, questões de prática e muito mais.

Notas de aula completas com diagramas
Assistente de aprendizagem com IA
Estude offline, a qualquer hora e em qualquer lugar
Disponível para Android, Windows, macOS e Linux

Disponível na aplicação Green Bridge

Transfira a aplicação Green Bridge CBT para o seu telemóvel ou computador para aceder a notas de aula completas, questões de prática e muito mais.

Notas de aula completas com diagramas
Assistente de aprendizagem com IA
Estude offline, a qualquer hora e em qualquer lugar
Disponível para Android, Windows, macOS e Linux

Pratique Questões Simuladas

Quer praticar questões simuladas sobre Implementation? Descarregue a aplicação Green Bridge CBT para aceder a questões simuladas e avaliações completas sobre este tópico.

Descarregar a aplicação na Google Play Store

Tudo o que precisas para te destacares no JAMB, WAEC e NECO.

Green Bridge CBT Mobile App
Assistente de Chat de Aprendizagem Personalizada com IA
Milhares de Questões de Exames Anteriores do JAMB, WAEC e NECO
Mais de 1200 Notas de Aula
Suporte Offline - Aprenda a Qualquer Hora, em Qualquer Lugar
Horário da Ponte Verde
Resumos de Literatura & Possíveis Perguntas
Acompanhe o Seu Desempenho e Progresso
Explicações Detalhadas para uma Aprendizagem Abrangente