Overhead expenses ₦1,500From the data above, compute the prime cost?
Detalhes da Resposta
The prime cost is the total cost of direct materials, direct labor, and direct expenses that are required to produce a product or service. In this case, we are given the following costs:
Direct material = ₦2,500
Direct labour = ₦5,000
Direct expenses = ₦1,000
To calculate the prime cost, we simply add up these costs:
Prime Cost = Direct Material + Direct Labour + Direct Expenses
Plugging in the numbers from the question, we get:
Prime Cost = ₦2,500 + ₦5,000 + ₦1,000
Prime Cost = ₦8,500
Therefore, the answer is ₦8,500.
In simpler terms, the prime cost is the total cost of the raw materials, labor, and other expenses that are directly involved in the production of a product or service, before overhead expenses are added.