Given: Direct material ₦2,500 Direct labour ₦5,000 Direct expenses ₦1,000 Overhead expenses ₦1,500From the data above, compute the prime cost?

Toets: JAMB UTME - Principles of Accounts - 2001 Vak: Financial Accounting

Vraag 1 Verslag

Given:

Direct material ₦2,500

Direct labour ₦5,000

Direct expenses ₦1,000

Overhead expenses ₦1,500From the data above, compute the prime cost?

Antwoorddetails
The prime cost is the total cost of direct materials, direct labor, and direct expenses that are required to produce a product or service. In this case, we are given the following costs: Direct material = ₦2,500 Direct labour = ₦5,000 Direct expenses = ₦1,000 To calculate the prime cost, we simply add up these costs: Prime Cost = Direct Material + Direct Labour + Direct Expenses Plugging in the numbers from the question, we get: Prime Cost = ₦2,500 + ₦5,000 + ₦1,000 Prime Cost = ₦8,500 Therefore, the answer is ₦8,500. In simpler terms, the prime cost is the total cost of the raw materials, labor, and other expenses that are directly involved in the production of a product or service, before overhead expenses are added.

Download de app in de Google Playstore

Alles wat je nodig hebt om uit te blinken in JAMB, WAEC en NECO.

Green Bridge CBT Mobile App
Persoonlijke AI Leerchat Assistent
Meer dan 200.000 IGCSE-, JAMB-, WAEC- en NECO-examenvragen.
Meer dan 1200 lesnotities
Offline ondersteuning - Leer altijd en overal
Dienstregeling Groene Brug
Literatuursamenvattingen & Potentiële Vragen
Volg je prestaties en vooruitgang.
Diepgaande Uitleg voor Uitgebreid Leren