Given: Depreciation of plant and machinery ₦1,600 Factory rent ₦650 Indirect wages ₦695 General indirect expenses ₦726 Lubricants ₦1,235 Carriage inwards ₦8...

Jarabawa: JAMB UTME - Principles of Accounts - 2021 Darasi: Financial Accounting

Tambaya 1 Rahoto

Given:

Depreciation of plant and machinery ₦1,600
Factory rent ₦650
Indirect wages ₦695
General indirect expenses ₦726
Lubricants ₦1,235
Carriage inwards ₦829
Factory power ₦350
Bank charges ₦612
Carriage outwards ₦2,900

Determine the total factory overhead cost