Given:Depreciation of plant and machinery ₦1,600 Factory rent ₦650 Indirect wages ₦695 General indirect expenses ₦726 Lubricants ₦1235 Carriage inwards ₦829...

Jarabawa: JAMB UTME - Principles of Accounts - 2000 Darasi: Financial Accounting

Tambaya 1 Rahoto

Given:Depreciation of plant and machinery ₦1,600

Factory rent ₦650

Indirect wages ₦695

General indirect expenses ₦726

Lubricants ₦1235

Carriage inwards ₦829

Factory power ₦350

Bank charges ₦612

Carriage outwards ₦2,900Determine the total factory overhead cost?