The data below shows the number of worker? employed in the various sections of a construction company in Lagos. Carpenters 24 Labourers 27 Plumbers 12 Plast...

Prüfung: WAEC SSCE - General Mathematics - 1992 (Objective) Fach: General Mathematics

Frage 1 Bericht

The data below shows the number of worker?
employed in the various sections of a construction
company in Lagos.



Carpenters 24 Labourers 27
Plumbers 12 Plasterers 15
Painters 9 Messengers 3
Bricklayers 18


If a worker is retrenched, what is the probability that he is a plumber or plasterer.
Antwortdetails
To calculate the probability that a retrenched worker is a plumber or plasterer, we need to first find the total number of workers in the company, and then find the number of workers who are plumbers or plasterers. The total number of workers in the company is: 24 (Carpenters) + 27 (Labourers) + 12 (Plumbers) + 15 (Plasterers) + 9 (Painters) + 3 (Messengers) + 18 (Bricklayers) = 108 The number of workers who are plumbers or plasterers is: 12 (Plumbers) + 15 (Plasterers) = 27 Therefore, the probability that a retrenched worker is a plumber or plasterer is: 27 (number of plumbers and plasterers) / 108 (total number of workers) = 1/4 So the correct answer is option D: 1/4.

Lade die App im Google Playstore herunter.

Alles, was du brauchst, um in JAMB, WAEC & NECO zu glänzen.

Green Bridge CBT Mobile App
Personalisierter KI-Lern-Chat-Assistent
Über 200.000 Prüfungsfragen für IGCSE, JAMB, WAEC und NECO.
Über 1200 Unterrichtsnotizen
Offline-Unterstützung - Lernen jederzeit und überall
Fahrplan der Grünen Brücke
Literaturzusammenfassungen & Potenzielle Fragen
Verfolgen Sie Ihre Leistung und Ihren Fortschritt
Detaillierte Erklärungen für umfassendes Lernen